Conditioning of the Military Goverment Building


Term of execution: 3 MonthsStatus of work: Completed

The works were carried out in the former Military Government building and consisted of the conditioning of 897.55 m2 of the 3,800 m2 of constructed area, which takes a third part of the total property to be used as a Civic Center.

The main areas of action have been the improvement of accessibility through Veeduría Street, the conditioning of the woodwork, the recovery of the original structure, the extension of the main staircase that linked the ground floors and first to facilitate access to the second floor, the installation of a panoramic elevator in the inner courtyard, also rehabilitated, and the provision of new facilities for electricity, heating, plumbing and fire protection systems.

The rehabilitation has focused mainly on the improvement of the existing space, the lighting through the interior patio and the overall improvement of accessibility, security, stability and functionality.